Here's the latest update from the project managers:
- Federal Government Grant – variation sought to agreement to mirror program with builder taking site slightly later. This has been submitted for review with the government department.
- Memorial – final endorsement received from trust 7 June 2021 enabling memorial to procced.
- Helen Black Oval - Underground services on Helen Black conduits installed, pits and cables ongoing – approx. completion July/August 2021
- Gordon Brown Oval - Underground services to Gordon Brown conduits installed, pits and cables ongoing - approx. completion July/August 2021
- ISAS Oval - Under Ground Services ongoing, pits and cables ongoing. Lighting footings have been installed.
- Main Building Works - sub base works completed - Building Plateau completed awaiting services to be installed before footings are excavated. Slab to be poured in coming weeks.
- Transportable Building Works - Mark up drawings currently submitted, Finalising approvals approx. completion October 2021