Here’s the latest update from the project managers:
Project was paused as a result of State-wide lockdown with works re-commencing.
- Lighting – underground services and conduits installed, pits and cables ongoing – approx. completion late August/September 2021. Delivery of light poles was impacted by a typhoon in China and pushed out a few weeks.
- Main structure – continued to progress.
- Memorial – civil works continuing.