Here’s the latest update from the project managers:
- Memorial – final endorsement received from trust 7 June 2021 enabling memorial to proceed. Order of parts has been palced.
- Helen Black Oval - Underground services on Helen Black conduits installed, pits and cables ongoing – approx. completion July/August 2021
- Gordon Brown Oval - Underground services to Gordon Brown conduits installed, pits and cables ongoing - approx. completion July/August 2021
- ISAS Oval - Under Ground Services ongoing, pits and cables ongoing. Lighting footings have been installed.
- Main Building Works - Slab to be poured next week.
- Transportable Building Works - Mark up drawings currently submitted, Finalising approvals approx. completion October 2021
- Attached – photos from site 22 June 2021 – photo includes lighting trenches on Helen Black oval.